| Hurricane proof waterfront house construction 2007-2009- the planning and construction process of Villa Lagoon Phase II Main House | ||||||||||
| Home | Planning | Blocks | Plans1 | Plans2 | Foundation | Site Prep | Blocks | 1st Slab | 1sr Slab | Slab Pour |
| Acid Stain | Crane | 1st Course | 2nd Course | 3,4,5 Course | Second Pour | 1sr Floor | Crane Repair | Half Way Up | 2008 | Top Floor Joists |
| Top Floor | Panels | Frieze | Top Floor Walls | Acid Stain Frieze | Acid Stain Con't | Cornice | Upper Story | Cornice & Panels | MgO & Evoba | Cornice & Trusses |
| Video | Top Rows-1 | Bulkhead | Month 15 | Month 16 | Exterior Completion | Roof | Interiors-1 | Steps | Insulation & Kitchen | MgO Board |
| Kitchen Counters | Tile Floors | Cement Tile-2 | Cabinets | Interior Decor | Cuban Ceiling | Saga of the Toilets | Interior Con't | Cement Tile Downstairs | ||
| Product Discussion Pages | ||||||||||
| Partners | DacArt in the News | Buy a Finished Dac-Art Home | Tankless Water Heaters |
Magnesium Oxide Boards-MgO | Concrete Bldg. Systems | Custom Garage Doors | Composite Decking |
House Numbers |
Concrete Floor Tile | |
Nov 2007--
|
|
|
| Mike and Don, our block layers have been doing tests with various grout products. We had a ton of rain down this way a week or so ago and one DAC-ART house, over in Gulf Breeze, FL has noticeable migration of water thru the grout they had used. We sure don't want that same problem, so we are re-considering what we have been using. We tried a new (to us) product from L & M Concrete Products, but it did not perform as well as a combination of Thoro brand products. The blocks were sealed on the bottom edge and grouted. The next day they were filled with water in the open cavity of the blocks. | |
|
|
|
| These openings were cut into the top blocks that will be the above ground basement for vents to be inserted. A nice looking, non-rusting brass or aluminum register can be screwed into the blocks to cover the opening later. A register with movable vents will be inserted in the vent holes. This is the west side. | The vent openings in the east elevation. |
I went to Memphis for a week. Along the way I
stopped at a roadside BBQ vendor. I bought a pulled pig sandwich, a Cornish hen
(he was out of ribs, I passed on the snout)
|
|
|
| The area under the porch was
filled with sand, wet and tamped down. The water didn't really have any
place to go, so it is real obvious that the grout mix that my guys
started with would not be watertight. This area of grout will have to be
removed and re-grouted. The wood boards are form boards for the porch's
slab that got poured the next day.
You can see the window and door openings now. |
|
|
|
|
|
|
The entrance stairs will hug the side of
the wall and come down both south and north. The ones on the south side
will require a couple more steps since the ground slopes towards the
water. The men dug a footing for the outside wall of DAC-ART blocks that
form the staircase.
Everything had to be inspected before we poured concrete. The inspector came Tues. Nov 13, 2007. The concrete was poured the next day, Wed. Nov 14, 2007. |
|
|
|
| The joists for the first floor are attached to a band of wood that is bolted into the DAC-ART blocks. We are using Georgia-Pacific manufactured joists from Swift Supply in Orange Beach, AL. | |
|
|
|
| When I got back after about a week's absence, the joists were all in place as was the rebar in the garage slab and the porch. | |
|
|
|
|
|
|
|
|
|
|
|
Next day, Wed, Nov 14, 2007 was a beautiful day to pour concrete. The pumper truck arrived and a series of concrete mixers showed up like clockwork. Some had interesting paint jobs. |
|
|
|
|
|
|
|
|
|
|
These workers are finishing the slab and it's newly poured concrete in the garage. |
|
|
|
The photo above is looking deep into a
stacked dry-stack block wall. You can see the rebar running laterally
and vertically. The wire near the top is the lift handle. This area
gets completely filled with concrete when the blocks are
back-filled.
The openings for the vents were boxed in so the back-fill concrete would not flow out thru them. |
By the time I got over here on Thursday , Nov 15, the sub-floor was in place and the temporary stairs from garage to first floor were in built.
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
At one time we talked about putting the washer and dryer in this area beside and under the stairs, i am glad we moved them upstairs. It would have been really cramped and this way we can make a nice wide staircase into the entrance hall. |
|
|
|
|
| The first floor feels so high
up. It is built to the new code that requires the living area be much
higher than when we built the Phase I. From this level we can look down
upon the Phase I guesthouse/ office. This floor, looking north in these
photos, will have the large entrance hall/ library and the guestroom and
bath. Both areas will be generously sized. The guest room will have
French doors out onto the porch. One of the nice advantages of being up
high on the waterfront side is that if the air is still and there are
'no-see-ums' about, there is often an absence of bugs and even a bit of
extra breeze the higher up you go.
I am looking into the possibility of using Magnesium Oxide Wall Boards in place of gypsum boards (Sheetrock) . So far they look like a great substitute. I have spoken to several of the importers. Luckily the Port of New Orleans is not too far ways. |
|
You can support this website by starting all Amazon purchases here, pls use our Amazon link.
03/02/2010
|
|
|
| Original Website Villa Lagoon Phase I completed in 2003 See the construction process of Phase I |
New Website-2007-2009 Phase II North Elevation w/ Frieze Construction of Phase II on this site. |