DAC-ART Villa Lagoon waterfront house construction 2007-2008- the planning and construction process of Villa Lagoon Phase II addition
 HOME  Planning  Blocks Plans 1 Plans 2 Foundation  Site  Blocks First Slab  First Slab  First Slab Pour
Page 1 Page 2 Page 3 Page 4 Page 5 Page 6 Page 7 Page 8 Page 9 Page 10 Page 11
Acid Stain Crane 1st Course 2nd Course 3rd,4th,5th Course  Second Pour  1st Floor Crane Repair Half Way Up 2008 Top Floor Joists
Page 12 Page 13 Page 14 Page 15 Page 16 Page 17 Page 18 Page 19 Page 20 Page 21 Page 22
TopFloor Panels  Frieze Top Floor Walls Acid Stain Frieze Acid Stain Con't Acid Stain Cornice Upper Story Cornice    
Page 22 Page 23 Page 24 Page 25 Page 26 Page 27 Page 28 Page 29 Page 30    
Product Discussion Pages
Partners     Tankless
Water Heaters
Magnesium Oxide Boards-MgO     Custom Garage Doors Composite
Decking
House
Numbers
Concrete Floor Tile

 

Feb 2008 Construction of Top Floor of Concrete House

Sat, Feb 28th 2008

We have had some rather grey weather, and then it turned cold. My guys just wear jackets and work any day they can, including a lot of weekends.

We are now placing blocks on the top floor. It is going really fast. Ryan, Mike's partner, now operates the crane part of the time. 

Chilly days with clouds sometimes make nice sunsets. I can't wait to be able to sit out on the top deck and enjoy the sunsets in a few months. 

We had two or three days with a ton of rain. All the dried up gator ponds out in the wildlife reserve are probably full now. 

You can see that we are still drying out around here. So much rain !
     


The blocks that were grouted together to do the testing of different grout formulas are now getting cut apart. 

Beautiful skies, warmer weather.

A good bit of time has been spent on cutting these column blocks for the porch lintels. These blocks will go on the porch to receive the long, strong lintel blocks that support the upper deck. 

Juan and Jose are still grouting the blocks using ladders. At some point we are going to need to rent a mechanical man-lift for them to grout the very top rows.

The wind is finally out of the south, so that is a great sign. We are suppose to have warm weather, sunny and up to 70 degrees this weekend so I will be working on my concrete acid stain designs on the blocks. 

You can see the old faded windsock blowing straight out on the pole. 



Home Planning My Blocks  Plans 1   Plans 2 Foundation Plans Site Prep Blocks Arrive First Slab Forms First Slab Prep

First Slab Pour

Concrete Acid Stain Slab Crane First Course
Blocks
Second Course
Blocks
3rd, 4th, 5th Row Blocks Second Pour First Floor Crane Repair Half Way Up Begin Top Floor Top Floor Joists
Top Floor Decking Panels &
Acid Stain
Concrete Acid Stain Top Floor Walls Acid Stain Frieze Acid Stain Con't Acid Stain Cornice Upper Story Cornice    
Product Discussion Pages  
  Tankless
Water Heaters
Hurricane
Windows & Doors

Composite
Decking

House
Numbers
Magnesium Oxide Boards-MgO        

Concrete FloorTile

Click Here for house plans on the Internet!!

ehouseplans.com

You can support this website by starting all Amazon purchases here, just click thru our link, but we can't track your purchases :o)

05/05/2008

Hurricane proof waterfront office and house

DAC-ART Villa on Alabama's Gulf Coast

Original Website
Villa Lagoon Phase I completed in 2003
See the construction process of Phase I
New Website
Phase II North Elevation w/ Frieze
Construction of Phase II on this site.

                                      
                                                                             
                                                                            