| DAC-ART Villa Lagoon waterfront house construction 2007-2008- the planning and construction process of Villa Lagoon Phase II addition | ||||||||||
| HOME | Planning | Blocks | Plans 1 | Plans 2 | Foundation | Site | Blocks | First Slab | First Slab | First Slab Pour |
| Page 1 | Page 2 | Page 3 | Page 4 | Page 5 | Page 6 | Page 7 | Page 8 | Page 9 | Page 10 | Page 11 |
| Acid Stain | Crane | 1st Course | 2nd Course | 3rd,4th,5th Course | Second Pour | 1st Floor | Crane Repair | Half Way Up | 2008 | Top Floor Joists |
| Page 12 | Page 13 | Page 14 | Page 15 | Page 16 | Page 17 | Page 18 | Page 19 | Page 20 | Page 21 | Page 22 |
| TopFloor | Panels | Frieze | Top Floor Walls | Acid Stain Frieze | Acid Stain Con't | Acid Stain Cornice | Upper Story | Cornice | ||
| Page 22 | Page 23 | Page 24 | Page 25 | Page 26 | Page 27 | Page 28 | Page 29 | Page 30 | ||
| Product Discussion Pages | ||||||||||
| Partners | Tankless Water Heaters |
Magnesium Oxide Boards-MgO | Custom Garage Doors | Composite Decking |
House Numbers |
Concrete Floor Tile | ||||
Sat, Feb 28th 2008
| We have had some rather grey weather, and then it turned cold. My guys just wear jackets and work any day they can, including a lot of weekends. | |
![]() We are now placing blocks on the top floor. It is going really fast. Ryan, Mike's partner, now operates the crane part of the time. |
|
|
Chilly days with clouds sometimes make nice
sunsets. I can't wait to be able to sit out on the top deck and enjoy
the sunsets in a few months.
We had two or three days with a ton of rain. All the dried up gator ponds out in the wildlife reserve are probably full now. |
![]() |
![]() |
![]() |
![]() |
![]() |
| You can see that we are still drying out around here. So much rain ! | |
![]() |
|
|
|
|
|
|
Beautiful skies, warmer weather. |
|
|
|
|
|
|
|
A good bit of time has been spent on cutting these column blocks for the porch lintels. These blocks will go on the porch to receive the long, strong lintel blocks that support the upper deck. |
|
|
|
|
|
|
|
| Juan and Jose are still grouting the blocks using ladders. At some point we are going to need to rent a mechanical man-lift for them to grout the very top rows. | |
|
|
The wind is finally out of the south, so that
is a great sign. We are suppose to have warm weather, sunny and up to 70
degrees this weekend so I will be working on my concrete acid stain
designs on the blocks.
You can see the old faded windsock blowing straight out on the pole. |
|
|
|
|
|
|
|
|
|
You can support this website by starting all Amazon purchases here, just click thru our link, but we can't track your purchases :o)
05/05/2008
|
|
|
| Original Website Villa Lagoon Phase I completed in 2003 See the construction process of Phase I |
New Website Phase II North Elevation w/ Frieze Construction of Phase II on this site. |