| Hurricane proof waterfront house construction 2007-2009- the planning and construction process of Villa Lagoon Phase II Main House | |||||||||||
| Home | Planning | Blocks | Plans1 | Plans2 | Foundation | Site Prep | Blocks | 1st Slab | 1sr Slab | Slab Pour | |
| Acid Stain | Crane | 1st Course | 2nd Course | 3,4,5 Course | Second Pour | 1sr Floor | Crane Repair | Half Way Up | 2008 | Top Floor Joists | |
| Top Floor | Panels | Frieze | Top Floor Walls | Acid Stain Frieze | Acid Stain Con't | Cornice | Upper Story | Cornice & Panels | MgO & Evoba | Cornice & Trusses | |
| Video | Top Rows-1 | Bulkhead | Month 15 | Month 16 | Exterior Completion | Roof | Interiors-1 | Steps | Insulation & Kitchen | MgO Board | |
| Kitchen Counters | Tile Floors | Cement Tile-2 | Cabinets | Interior Decor | Cuban Ceiling | Saga of the Toilets | Interior Con't | Cement Tile 1st FL | |||
| Product Discussion Pages | |||||||||||
| Partners | DacArt in the News | Buy a Finished Dac-Art Home | Tankless Water Heaters |
Magnesium Oxide Boards-MgO | Concrete Bldg. Systems | Custom Garage Doors | Composite Decking |
House Numbers |
Concrete Floor Tile | ||
Sat, Feb 28th 2008
| We have had some rather grey weather, and then it turned cold. My guys just wear jackets and work any day they can, including a lot of weekends. | |
![]() We are now placing blocks on the top floor. It is going really fast. Ryan, Mike's partner, now operates the crane part of the time. |
|
|
Chilly days with clouds sometimes make nice
sunsets. I can't wait to be able to sit out on the top deck and enjoy
the sunsets in a few months.
We had two or three days with a ton of rain. All the dried up gator ponds out in the wildlife reserve are probably full now. |
![]() |
![]() |
![]() |
![]() |
![]() |
| You can see that we are still drying out around here. So much rain ! | |
![]() |
|
|
|
|
|
|
|
|
Beautiful skies, warmer weather. |
|
|
|
|
|
A good bit of time has been spent on cutting these column blocks for the porch lintels. These blocks will go on the porch to receive the long, strong lintel blocks that support the upper deck. |
|
|
|
|
|
|
|
| Juan and Jose are still grouting the blocks using ladders. At some point we are going to need to rent a mechanical man-lift for them to grout the very top rows. | |
|
|
The wind is finally out of the south, so that
is a great sign. We are suppose to have warm weather, sunny and up to 70
degrees this weekend so I will be working on my concrete acid stain
designs on the blocks.
You can see the old faded windsock blowing straight out on the pole. |
|
|
|
|
|
|
|
|
|
You can support this website by starting all Amazon purchases here, pls use our Amazon link.
07/08/2010
|
|
|
| Original Website Villa Lagoon Phase I completed in 2003 See the construction process of Phase I |
New Website-2007-2009 Phase II North Elevation w/ Frieze Construction of Phase II on this site. |